by Valerie Beelman
Anderson & Associates is working for Turner Construction on this project and has already completed staking for the garage and building locations. Additionally, A&A was asked to monitor buildings that adjoin the work site as the four-story garage was excavated. Survey Manager Neil Martin says, "We monitored these buildings for four to six months, to check for moving or shifting." Additionally, A&A was asked to complete a survey of utilities, set the property corners for each structure, and will be required to survey the final building corners, location, and building height. The project is currently nine months underway with an estimated one and a half to two years remaining. Crews recently completed excavation for the below ground garage and securing walls and continue to work on the construction of the garage structure.