"It’s never crowded along the extra mile."   Wayne Dyer

 

We're Working For...

Fredericksburg-Stafford Park Authority, Va.- Design, bidding, and construction administration for approximately 4500 linear feet of 10 ft. wide paved trail, including two pedestrian bridges, retaining walls, and connections with other nearby trail systems for the Bicycle/Pedestrian Trail Phase 3 in the St. Clair Brooks Park area, and between the Chatham and Falmouth bridges on the Stafford County side of the over the Rappahannock River.

Smyth County, Va.- Preparing a preliminary engineering report for a water line extension to serve several customers and alleviate poor water quality in the Fox Valley area. Additionally, designing 2,200 linear feet of 6" water line to serve approximately 15 customers in the Axum/Longleaf Lane area.

Town of Purcellville, Va.- Design of approximately 250 linear feet of new sidewalk along one side of 23rd Street to connect to the existing sidewalk system along Main Street.

Town of Pearisburg, Va.- Performing a study of the Town water system to evaluate the effects of the Route 100 water system connection.

Congrats!

Congratulations to Jon Greene, Tri-Cities Project Manager, and his wife on the birth of their son, Jeremiah Thomas.


Welcome

Daniel Hobson, Greensboro Survey Technician

Heather Jessup, Greensboro Project Engineer

Chris Joyce, Greensboro Survey Technician

Cindy Levin, Fredericksburg Survey Technician

Sherri Rogers, Tri-Cities GIS/Survey Technician

Drew Warmack, Fredericksburg Survey Technician

Allison White, Blacksburg HR Generalist

Jonathan Wishart, Greensboro Project Manager

 


 

bottom_bar copy.jpg (6493 bytes)
A&A Homepage / Browse Other Issues